10 men take 4 days to complete the the task of concreting a road how many days world 8 men take
Attachments:
Answers
Answered by
2
Answer:
hi friend. mark my answer brainliest for more help
Step-by-step explanation:
10 men take 4 days
so 1 man takes 4*10 days
8 men take 40/8 = 5 days
Answered by
0
Answer: 8 men would take 5 days to complete the task.