10 men work in 55 days. then how many men do same work in 25 days
Answers
Answered by
0
10 men ~ 55 days
x men ~ 25 days
10/x = 55/25
10/x = 11/5
11x = 5 × 10
11x = 50
x = 50 : 11
x = 4,55 ≈ 5 men
x men ~ 25 days
10/x = 55/25
10/x = 11/5
11x = 5 × 10
11x = 50
x = 50 : 11
x = 4,55 ≈ 5 men