10 men, working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the work in 12 days ?

A) 4 hours a day B) 5 hours a day C) 6 hours a day D) 7 hours a day

Answers

Answered by wwwseenalingampalli
0

Answer:

6 hours a day

Step-by-step explanation:

pls mark as brainlist

Answered by riya1347
0

Answer:

c)6 hours a day

Step-by-step explanation:

To complete the work in 18 days 10 men work 6 hours day

To complete the work in 18 days 1 man work (10 x 6) hours a day

To complete the work in day 1 man will work (6 x 10 x 18) hours in a day (less days, less men, more hours)

To complete the work in 1 day 15 men will work

15

(6×10×18)

hours a day

∴ To complete the work in 12 days 15 men will work

12×15

6×10×18

hours a day

(more days, more men, less hours) = 6 hours a day.