10 men working 8 hours a day, can finish a work in 12 days. In how many days can 12 men working 5 hours a day finish the same work?
Answers
Answered by
1
Answer:
15
Step-by-step explanation:
YourAnswer
Now,
➡️ the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 men in x days
✔working 8 hours per day.
➡️12*8*x =10*16*9
➡️We will get the value of x = 15.
=> So they will need 15 days to complete the same amount of work.
Answered by
0
Step-by-step explanation:
Given: 10 men work 8 hours a day and complete work in 12 days.
To find: The number of days it takes for 12 men working 5 hours a day to complete work.
For calculation of the number of days:
We know that the work done by 10 men working 8 hours would be equal to work done by 12 men in 'x' days:
⇒
⇒
⇒
⇒
It will take 16 days for 12 men working 5 hours a day to complete work.