10 men working for 5 hours a day for 6 days Mow and area of 5 if there are 8 men working 4 hours a day to mow 4 acres of land, how many days will it take
Answers
Answer:
6 days
Step-by-step explanation:
we know,
Work=men*hours*days
here work is mow the land
10 men working for 5 hours a day for 6 days Mow and area of 5
5 acres=10 men*5 hours*6 days -----(1)
if there are 8 men working 4 hours a day to mow 4 acres of land, how many days will it take
let x be days
4 acres=8 men*5 hours* x days -----(2)
by dividing (1) by (2)
5 acres/4 acres=10 men*5 hours*6 days/8 men*5 hours* x days
x days=6
Total hours of work
=Number of workers×days × hours per day
=10×6×5
=300
Total hours required
That is a total of 300 hrs required to mow 5 acres
Time for mowing one acre=300/5 =60 hrs
Time for mowing 4 acres=60×4
=240 hrs
If there are 8 men and 4 hours of work per day
Amount of time per day=8×4 =32 hrs
Days required= total time/ time per day
=240/32
=7.5 days
Therefore,
Number of days required = 7.5 days