10 people take 15 days to dig a land, how many people are required to dig the
same land in 25 days?
please answer in detail
Answers
Answered by
1
Answer:
Step-by-step explanation:
if 10 people take 15 days then
= 15/10
=1.5 is work done by 1 person so for 25 days
= 16 people are needed