10 person can finish a work in 28 days .how many person can finish the work in 10 days
Answers
Answered by
3
Step-by-step explanation:
10 person can do work in 28 days
1 person can do work in 28×10 days
Then, number of persons requires to do work in 10 days
= 280/10 = 28 persons.