10 persons can finish a piece of work in 15 days. in how many days the same work can be done by 25 persons
Answers
Answered by
0
1 person = 15 × 10 = 150 days. 25 persons = 150/25 = 6 days. Hence, 25 persons can finish the same work in 6 days.