4 people working 6 hours a day can do a work in 14 days. In how many days can 7
people working 3 hours a day, finish the job?
11shivam108:
Answer 16 hai
Answers
Answered by
0
Answer:
16
Step-by-step explanation:
4 * 6 * 14
__________
7 * 3