10 women can complete a work in 7 days and 10 children take 14 days to complete the work how many days will 5 women and 10 children take to complete the work
Answers
Answered by
0
Answer:
all we should be added
10+7+10+14+5+10
Answered by
3
Answer:
Step-by-step explanation :
The work is same
So....
10W×7 = 10C×14
1W = 2C
So. (5W =10C)
Now..
10 children can complete that work in 14 days..
So 1 child will complete that work in 140days
So (5 women + 10 Children) Or 20 children
Will complete that work in
140/20 = 7days