Math, asked by kingajay986, 4 months ago

10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete work
Select one:​

Answers

Answered by pavi526
2

Answer:

it takes 24 days

hope it helps

pls mark me as brainliest

Answered by mirahmedkamili
1

Answer:

7 days

Step-by-step explanation:

It takes 10 women to complete work in 7 days

which means 5 women will complete the work in 14 days.

14 days is also the time in which 10 children will complete the work.

So

5 women in 7 days will complete 50% of the work and in the same time (7days) 10 children will complete the 50% of the work...

So it will take 7 days for 5 women and 10 children to complete the work.

Hope this answers the question.