Math, asked by rizwanaabdulrahim77, 8 months ago

10 women can finish a quilt in 3 months. How long will 4 women take

Answers

Answered by Kanagaraju
1

Answer:

7months 15days

To complete work, 10 women worked for 3months

Total woman power = 10 ×90 = 900

no of days, 4 women to complete same work

= 900/4 = 225 days = 7 months 15days