Math, asked by bilalhiba853, 2 months ago

10 women completed their handicraft work in 8 days. If the work is to be finished in half the time
then how many more women would be needed?

Answers

Answered by Xxaditi2311xX
0

what we have to find-: Women Needed

What is given-:

Number of Women and Number of days

How we have to find answer of question-:

(KINDLY REFER BELOW!!)

Woman completed handicraft in = 10 days

Women Needed to do so = 8 women

Now, if the work is to be finished in half the time = 8/2=4 days

Women needed = x= 10/x=8/4 = (Cross Multiply )

= 40/8x=5

5More women needed =Total women to complete work in half a time = 5+8=13