10 workers build a wall in 4 days. How many workers are needed to build 4 such walls in 5 days?

Answers

Answered by sharmakrishna15jan
1

Answer:

16 worker will needb to built such wall in 5 days

Answered by bnida0392
0

Answer:

16 workers. ..........