10 workers can make a machine in 15 days. 5 more workers join after 3 days.find the total number of days in which the machine will be prepared.
Answers
Answered by
6
Answer:4 days
Step-by-step explanation:·
people days
10 - 15
days left after 3 days=12
therefore 10 men in 8 days
thereby 1 man take 80 days
after 3 days 5 workers join
so total workers= 15
∴60/15 = total days=4 days
Answered by
11
Answer:
Total number of days = 11
Step-by-step explanation:
Remaining days left for completion of the machine => 15-3= 12
So if 10 men worked for 12 days
Then, Work done by them in 12 days => 12*10= 120
Now, this part (120) of the work will be done by (10+5=15) men
So, no of days required for completion of the same work=> 120/15= 8
Now total no of days required for completion of the work = 8+3 = 11 days (since, previously 3 days of work was done)