10 workers can paint a house in 30 days how many days will 15 workers take​

Answers

Answered by pinki12
11

Answer:

10 workers work for=30days

1 worker work for = 30*10

15 workers work for=( 30 * 10)/15

= 20 days

PLEASE MARK ME AS BRAINLIEST

THNX IN ADVANCE

Answered by achala25
2

Answer:

15 workers will take 20 days to paint house