100 men started working to complete a work in 50 days.After working 8hours/day they had completed 1/3rd of the work in 25 days.How many men should be hired so that they will finish the work in time by working 10 hours/day.
7th feb Elitmus.
Answers
Answered by
0
Answer:
Step-by-step explanation:
https://www.google.com/amp/s/m4maths.com/amp/155425.html
Here you go.