. 100 men working 7 hours per day can finish a work in 16 days. If 140 men are engaged to finish the work in 10 days, how many hours per day should they work? ​

Answers

Answered by shamimaafroj04
2

Answer:

8 hours

Step-by-step explanation:

100 men finish a work in 16 days by working = 7 hour

1 men " " 1 " " " =16×100×7

140 " " " 10 " " " =

11200÷(140×10) = 8 hours.