Math, asked by aayush128, 1 year ago

100 PEOPLE CAN CONSTRUCT A BRIDGE IN 30 DAYS.HOW MANY MORE PEOPLE NEED TO BE EMPLOYED IF THE BRIDGE NEEDS TO BE COMPLETED IN 24 DAYS?

Answers

Answered by siddiquiamaan
4

Answer: use the case of inverse variation and it would come as 125 people .

So extra people will be 125-100 i.e.

25 people

Step-by-step explanation:


Answered by Shaanraj
5
Hey mate!!!

 <b >Here is your answer ;</b >

Given,
It takes 30 days to construct a bridge by 100 people

Then,
It takes 1 day to construct a bridge by (30 * 100 )people
[inversely proportionality]

Thus,

It takes 24 days to construct a bridge by
 \frac{(30 * 100)} {24}

= 125 people.

 <b ><big ><marquee >I hope it helps you #need more brainliests marks
Similar questions