Math, asked by tamantapo61, 2 months ago

103. A can do a piece of work in 8 days, which B
alone can do in 10 days. In how many days both
working together can do it?
A. 6/10
.B.9/10
C. 40/9
D. 80/5​

Answers

Answered by viya77777
1

Step-by-step explanation:

bothA and B can do it in 40/9 days