109. A and B together can do a piece of work in 30 days. B and
C together can do it in 20 days. A starts the work and
works on it for 5 days, then B takes up and works for 15
days. Finally C finishes the work in 18 days. The number
of days in which C alone can do the work when doing it
separately is
(2) 40 (6) 120 (C) 60
(d) 24
Answers
Answer:
Option d) 24
Step-by-step explanation:
According to question
A and B together do a piece of work in 30 days.
Means, A + B = 30 days
Similarly,
B and C together do a piece of work in 20 days.
B + C = 20 days
LCM of 20 and 30 is 60.
Work done by A and B in 1 day = 60/30
= 2 units
Work done by B and C in 1 day = 60/20
= 3 units
So,
A + B = 2 and B + C = 3 ____ (eq 1)
A starts the work and work on it for 5 days.
A = 5 days
Similarly, B and C starts the work and work on it for 15 and 18 days.
B = 15 days and C = 18 days
We have to find the number of days in which the C alone do the work.
A starts the work and works on it for 5 days, then B takes up and works for 15 days. Finally C finishes the work in 18 days.
Also, work done by both A and B is 60 units.
So,
- A = 5 days
- B = (5 + 10) days
- C = (10 + 8) days
Remaining work = 5A + 15B = 60
= 5(A + B) + 10(B + C) = 60
= 5(2) + 10(3) = 60 [From (eq 1)]
= 10 + 30 = 60
= 60 - 40
= 20 units
So, work done by C in 8 days
= 20/8
= 5/2 unit/day
Total work = 60
Time taken by C alone to complete the work = (60 × 2)/5
24 days
Answer:
24 days
Step-by-step explanation:
A and B together can do the work in
30 days
and
B and c together can do it in 20 days.
LCM of 30 and 20 is 60
So total work is 60 unit's
( A + B ) per day work is 60/30 = 2 unit's
and
( B + C ) per day work is 60/20 = 3 unit's
now,
A starts the work on it 5 day's
then B takes up and work per 15 days
C finished remaining work in 18 days
this means
A = 5 days
B = ( 5 + 10 ) days
C= ( 10 + 8 ) days
Now work done by ( A + B ) in 5 days
is = 2 × 5 = 10 unit's
and work done by ( B + C) in 5 days
is = 3 × 10 = 30 unit's
total work finished till now
10 + 30 = 40 unit's
remaining work is 60 - 40 = 20 unit's
Here we know C does remaining 20 unit's
in 8 days
C efficiency is work/day = 20/8 = 5/2
Hence time taken by C alone to
complete the whole work is,
( 60/5 ) × 2 = 12 × 2 = 24 days.