10man complete 1 wall in 8 days how many man complete wall in half day
Answers
Answered by
0
Answer:
Step-by-step explanation:
Number of men work inversely proportion to number of days to finish
x= number of men
y=number of day
y=k/x
8=k/10
80=k
equation is
y =80/x
constant =k= 80
so when want to finish work in 1/2 day how may men required?
means when y= 1/2 what is value of x
y=80/x
1/2 = 80/x
by cross multiplication
x =160
so 160 men are required to finish work in 1/2 day
So number of men added is 160-10=150