11. A contractor undertakes to build a wall
1000 m long in 50 days. He employs 56 men,
but at the end of 27 days, he finds that only
448 m of wall is built. How many extra men
must the contractor employ so that the wall is
completed in time? ​

Answers

Answered by uparihar771
2

Answer:

Number of men employed in the beginning = 56

Length of wall = 1000 m No. of days = 50

In the time of 27 days, only 448 m of wall was completed

Remaining period = 50 – 27 = 23 days

and length of wall to be completed = 1000 – 448 = 552

Now in 27 days, 448 m long wall was completed by = 1000 m

in 1 day, 448 m long was completed by = 56 x 27

inf 1 day, 1 m long wall will be completed by

= (56 × 27)/448

And in 23 days 552 m long wall be completed

by = (56 × 27 × 552)/(448 × 23) men

= (1 × 27 × 24)/8 = 81 men

∴ No. of extra men required

= 81 – 56 = 25 men

Step-by-step explanation:

Hope this answer helps plz mark me as brainliest