11. If 8 men can take 12 hours to stitch 16 suits, how
many hours will 15 men take to stitch 50 suits ?
(a) 20 hours
(b) 15 hours
(c) 24 hours
(d) 22 hours
Answers
Answered by
1
Answer:
men. hours. Nos
8. 12. 16
15. x=? . 50
X = 8/15x12x 50/16 = 20 hrs
2ohrs is the answer
Answered by
0
Answer:
225 hrs
Step-by-step explanation:
8 men take 12 hours to stitch 16 suits.
then,
time taken by 1 man=12/8=1.5 hrs
time taken by 1 man for 1 suit=1.5/16
=0.09 hrs
time taken by 1 man for 50 suit=0.09*50
=4.5hrs
time taken by 15 men for 50 suits=225 hrs