Math, asked by shabari383, 4 months ago

11. Vikas and Mohan working together can complete a work in 6 days. If Vikas alone completes the same work in 10 days, in how many days Mohan alone can complete the same
work?
12 days
10 days
15 days
None of these
20 ratio will be 2.1
Their nresent ages are:​

Answers

Answered by YTAGORERAVINDRASREE
3

Answer:

15 days

Step-by-step explanation:

vikas 1 day work= 1/10

vikas and mohan 1 day work= 1/6

mohan 1 day work= 1/6-1/10= 1/15

so mohan takes 15 days to complete the work.


YTAGORERAVINDRASREE: please mark as brain list
YTAGORERAVINDRASREE: please
YTAGORERAVINDRASREE: please mark
Answered by ravilaccs
2

Answer:

The correct answer is option C

Step-by-step explanation:

Vikas and Mohan together can complete the task in 6 days. So, in one day, they will complete 1/6 part of the task. Therefore, (Vikas + Mohan)'s one-day work will be =1/6

Similarly, Vikas's one-day work =1/10

Therefore, Mohan's one day work =(1/6) - (1/10) = 2/30 = 1/15

In one day Mohan completes the 1/15 part of the work so he will complete the entire work in 15 days.