112 men can build a railway tunnel in 72 days how many more men will be required to build the tunel in 48 days? (unitary method)
Answers
Answered by
33
In 72 days work will be completed by 112 men,
then
in 1 day work will be completed by 112×72 men,
then
in 48 days work will be completed by (112×72)/48 men =168 men
then
in 1 day work will be completed by 112×72 men,
then
in 48 days work will be completed by (112×72)/48 men =168 men