12. 30 men can produce 1500 bolts in 24 days working 6 hours a day. In how many days can 18 men
produce 1800 bolts working 8 hours a day?
(a) 63
(b) 36
(C) 18
(d) 45
Answers
Answered by
3
Answer:
36
Step-by-step explanation:
It is an MDH question :
Man =30 , Days = 24, Hours = 6, Work = 1500
Man =18 , Days = d, Hours = 6, Work = 1800
MDH/W = mdh/w
⇒ 30x24x6/1500 = 18xdx6/1800
⇒ d = 36