12. A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
(i) How long will it take them to do the work together ? (ii) In what time can each finish it working alone ?
Answers
Answered by
3
Answer:Given : A and B can do a piece of work in 40 days, B and C in 30 days and C and A in 24 days. To find : In what time can each finish it working alone? Together they take A+B+C= 20 days
hope helped
Step-by-step explanation:
thx to my answer and mark it as brain list answer