12. A and B can do a work in 8 days, B and C in
12 days, and A and C in 16 days. In what time
could they do it, all working together?
Answers
★Given:-
- A and B can do a work in 8 days
- B and C in 12 days
- A and C in 16 days
★To find:-
- In what time could they do it, all working together?
★Solution:-
According to question,
(A+B)'s 1 day work = 1/8
(B+C)'s 1 day work = 1/12
(A+C)'s 1 day work = 1/16
Then, 1 day work of (A+B) , (B+C) &(A+C) will be:-
⇒[(A+B)+(B+C)+(A+C)]
⇒1/8 + 1/12 + 1/16
⇒(6 + 4 + 3)/48 = 13/48
And,
⇒[(A+B)+(B+C)+(A+C)]
⇒A+B + B+C + A+C
⇒2(A+B+C)
Therefore,
⇒2(A + B + C)’s 1 day work = 13/48
Then,
(A + B + C)’s 1 day work:-
⇒ 13/48 × 1/2
⇒ 96/13 days
⇒ 7.384 days.
Hence,
All working together can finish it in 7.384 days.
_______________
Given : -
Given A and B together can do a piece of work in 8 days.
B and C together can do the same piece of work in 12 days.
A and C together can do the same piece of work in 16 days.
Concept : -
Work done on each day = (total no. of units of work ) / (total no. of days required).
Solution : -
Let the total work be of 48 units (∵ L.C.M of 8 , 12 , 16 )
Then,
Work done by A and B together each day = 48/8 = 6 units per day.
Work done by B and C together each day = 48/12 = 4 units per day.
Work done by A and C together each day = 48/16 = 3 units per day.
Now when all together are working together,
work done on each day = ( 6 + 4 + 3 )/2 = 13/2 units per day.
No. of days required to complete by all together (D) = [ 48 / ( 13/2 ) ]
∴ D = 96/13 days (or) 7.384 days .