12 आदमी दिन भर काम कर किसी काम को 66 दिन मो समप्त करता है लेकिन उसमे से 3 सिर्फ आधा समय तक तथा 3 सिर्फ चौथाई समय तक काम करते है। तो काम कितने दिन मे समाप्त होगा?
Answers
Answered by
2
Answer:
113 1/4
Step by step explanation:
let Total work = 12 × 66 units
3×66/2 + 3 × 1/4* 66 + 6(rest)× x = 12 × 66
x = 107.25 = 107 1/4
work will be finished in
=3 +3 + 107 1/4 = 113 1/4 days
Answered by
0
Answer:
The final answer is 107.25.
Step-by-step explanation:
We have 12 men working a job. If they work for the whole day, They can complete the work within 66 days. However 3 of them work for half the time and 3 work a quarter of the time. We need to find the total days needed to complete the job.
12 * 66 = 3 * 66 / 2 + 3 * 66 / 4 + 6 * x
792 = 99 + 49.5 + 6x
792 - 148.5 = 6x
6x = 643.5
x = 643.5 / 6 = 107.25
The work will be completed within 107.25 days.
What is work done
https://brainly.in/question/1828896
Similar problems
https://brainly.in/question/10351521
#SPJ2
Similar questions
Political Science,
5 months ago
Science,
5 months ago
Biology,
10 months ago
Computer Science,
1 year ago
Biology,
1 year ago