12 boys can do a piece of work in 16 days. in how many days can 6 boys do the same work
Answers
Answered by
0
Answer:
32 days 6boys can do the work
Answered by
0
Answer:
32 days
Step-by-step explanation:
12 boys can do a piece of work in 16 days.
Average no of days a boy takes is 16*12 = 192 days
6 boys do the same work in (192 / 6) = 32 days