Math, asked by mannuhalikar, 10 months ago

12 children and 15 men complete a certain piece of work in 7 days. If each child takes twice the time taken by a man to finish the work, in how many days will 14 men finish the same work? ​

Answers

Answered by AnonymousUser0
1

Answer:

20

Step-by-step explanation:

DAYS

Answered by ashfaknawshad
0

Answer:

Step-by-step explanation:

Capacity of 2 children =Capacity of  1 man

12 c + 15 m = 7 days

6 m + 15 m = 7 days

21 m = 7 days

It means 21*7 man days for one man

147 man days / 14 men = 10.5 days

If understood mark as brainliest

Similar questions