Math, asked by shivangi7862, 1 year ago

12 labourers can plough a field completely in one week. After starting the work, 4 labourers leave after 3 days. After one week what part of the field would be left unplugged?​

Answers

Answered by subrataana9349
0

Answer:

Step-by-step explanation:

12x = 18(x-5)

12x = 18x - 90

90 = 18x - 12x

90 = 6x

x= 157 years agoHelpfull