12 man can complete 1/3 of the work in 8 days. in how many days can 16 man complete that work.
Answers
Answered by
0
Your answer is in attached picture
THANK YOU!! & PLZ FOLLOW ME FOR MORE ANSWERS ^-^
Attachments:
Answered by
0
Answer:
20 days
Step-by-step explanation:
12 man can do work 1/3 work in 8 days
So they can complete full work in 24 days
So 1 man can complete 1/12 work in 24 days
So 1 man can complete 1/(12×24) work in 1 day
Thus 16 man can complete 16/(12×24) work in 1 days
=> 1/20 work in 1 day
Hence they can complete the full work in 20 days