12 man can complete a work in a 8 days three days after they started the work 3 more man joins them in how many days will all of them together complete the remaining work
Answers
Answered by
10
work done by 12men in 1day = 1/8
and by 1man in 1day = 1/96 and in 3days = 3*(1/96)= 1/32
the remaining work= 31/32
time taken by 1man= 31/32÷ (1/96)= 93
and by 15 men= 93/15= 6days 1/5 days
and by 1man in 1day = 1/96 and in 3days = 3*(1/96)= 1/32
the remaining work= 31/32
time taken by 1man= 31/32÷ (1/96)= 93
and by 15 men= 93/15= 6days 1/5 days
Answered by
9
Answer:
They altogether complete remaining work in 4 days.
Step-by-step explanation:
Given : Twelve men can complete a work in 8 days.
To Find : three days after they started the work 3 more man joins them in how many days will all of them together complete the remaining work
Solution :
12 men 1 day work =
12 men 3 days work =
Remaining work =
After 3 days 3 more men joined them.
1 men 1 day work =
15 men 1 day work =
So, 15 men complete part of work in days = 1
15 men complete whole work in days =
15 men completepart of work in days :
=
=4
Hence they altogether complete remaining work in 4 days.