Math, asked by amitgarg36944, 11 months ago


12 man can do a piece of work in 12 days if 6 man left the work after 6 days then
in how many days rest people will do the Work
(a)20 day
(b) 18 day
(c) 16 day
(d) 12 day​

Answers

Answered by arunashah1302
0

Answer:

18.......................

Similar questions