Math, asked by vaishnavam0645, 7 months ago

12 men 9 hours per day to complete the 40% of the work in 30 day. The rest work is done by 15 men, 6 hour per day. Then work done in how many days.

Answers

Answered by kirtinevermind
3

Step-by-step explanation:

We know this:

If men changed by n times, time is changed by (1/n) of the initial time.

Initial time 10*8 = 80 hours.

Final time 8*15 = 120 hours.

(1/n) of 80 = 120 implies n = (2/3)

The number of men required is (2/3) of 12 = 8

The work involves 12*8*10 = 960 man-hour-days for its completion.

So the number of men required to complete the same work in 8 days, working 15 hours a day = 960 man-hour-days/8*15 hour-days = 8 men.

Answered by talasilavijaya
0

Answer:

The rest of the work is completed in 54 days.

Step-by-step explanation:

Given the number of men working, M_1= 12

Number of days worked, D_1= 30

Number of working hours per day, H_1= 9

Completed work, W_1= 40%

Thus the remaining work,  W_2=100-40=60\%

To complete 60%, number of men working, M_2= 15

Number of working hours per day, D_2= 6

Let the number of days working, D_2= x

In the case of time and work, if M_1 men do W_1 work in D_1 days for H_1 hours per day and M_2 men do W_2 work in D_2 days for H_2 hours per day, then      

\dfrac{M_1\times D_1\times H_1}{W_1} = \dfrac{M_2\times D_2\times H_2}{W_2}

Substituting the given values,

\dfrac{12\times 30\times 9}{40} = \dfrac{15\times x\times 6}{60}

\implies x=\dfrac{12\times 30\times 9\times 60}{40\times15\times  6} = 3\times 2\times 9=54

Therefore, the rest of the work is completed in 54 days.

For more problems

https://brainly.in/question/49052377

https://brainly.in/question/3575430

Similar questions