12 men 9 hours per day to complete the 40% of the work in 30 day. The rest work is done by 15 men, 6 hour per day. Then work done in how many days.
Answers
Step-by-step explanation:
We know this:
If men changed by n times, time is changed by (1/n) of the initial time.
Initial time 10*8 = 80 hours.
Final time 8*15 = 120 hours.
(1/n) of 80 = 120 implies n = (2/3)
The number of men required is (2/3) of 12 = 8
The work involves 12*8*10 = 960 man-hour-days for its completion.
So the number of men required to complete the same work in 8 days, working 15 hours a day = 960 man-hour-days/8*15 hour-days = 8 men.
Answer:
The rest of the work is completed in 54 days.
Step-by-step explanation:
Given the number of men working,
Number of days worked,
Number of working hours per day,
Completed work,
Thus the remaining work,
To complete 60%, number of men working,
Number of working hours per day,
Let the number of days working,
In the case of time and work, if men do work in days for hours per day and men do work in days for hours per day, then
Substituting the given values,
Therefore, the rest of the work is completed in 54 days.
For more problems
https://brainly.in/question/49052377
https://brainly.in/question/3575430