12 men can build a wall in 15 days. They work for 3 days and then the contractor brings a team of 18 men to complete the work. How many days will they now take to complete the remaining work?
Answers
Step-by-step explanation:
The time taken by 18 men to build the remaining wall is 8 days .
Step-by-step explanation:
Given as :
Let The 18 man can build the remaining wall in d days
Time taken by 12 men to build a wall = 15 days
i.e 12 men in 15 days make 1 wall
Or, 12 men in 1 day make \dfrac{1}{15}
15
1
wall
∴, 12 men in 3 days make \dfrac{1}{15}
15
1
× 3 wall
i.e 12 men in 3 days make \dfrac{1}{5}
5
1
wall
Again
Contractor bring team of 18 men to complete the remaining work
Remaining work = 1 - \dfrac{1}{5}
5
1
Or, Remaining work = \dfrac{5-1}{5}
5
5−1
∴ Remaining work = \dfrac{4}{5}
5
4
Now,
∵ \dfrac{men\times day}{work}
work
men×day
= constant
So, \dfrac{12\times 3}{\frac{1}{5}}
5
1
12×3
= \dfrac{18\times d}{\frac{4}{5}}
5
4
18×d
Or, 4 × 12 × 3 = 18 × d
∴, d = \dfrac{144}{18}
18
144
i.e d = 8 days
So, The time taken by 18 men to build the remaining wall = d = 8 days