12 men can build a wall in 15 days they work for three days and then the contracter bring a team of 18 workers to complete the work how many days will they now take to complete the remaining work
Answers
The time taken by 18 men to build the remaining wall is 8 days .
Step-by-step explanation:
Given as :
Let The 18 man can build the remaining wall in d days
Time taken by 12 men to build a wall = 15 days
i.e 12 men in 15 days make 1 wall
Or, 12 men in 1 day make \dfrac{1}{15}
15
1
wall
∴, 12 men in 3 days make \dfrac{1}{15}
15
1
× 3 wall
i.e 12 men in 3 days make \dfrac{1}{5}
5
1
wall
Again
Contractor bring team of 18 men to complete the remaining work
Remaining work = 1 - \dfrac{1}{5}
5
1
Or, Remaining work = \dfrac{5-1}{5}
5
5−1
∴ Remaining work = \dfrac{4}{5}
5
4
Now,
∵ \dfrac{men\times day}{work}
work
men×day
= constant
So, \dfrac{12\times 3}{\frac{1}{5}}
5
1
12×3
= \dfrac{18\times d}{\frac{4}{5}}
5
4
18×d
Or, 4 × 12 × 3 = 18 × d
∴, d = \{144}{18}
18
144
i.e d = 8 days
So, The time taken by 18 men to build the remaining wall = d = 8 days
Hence, The time taken by 18 men to build the remaining wall is 8 days . Answer