12 men can build a wall in 15 days they worked for three days and then the contractor bring a team of 18 main to complete the work how many days will they now take to complete the remaining work?
Answers
Answered by
0
Answer:
The time taken by 18 men to build the remaining wall is 8 days .
Step-by-step explanation:
Given as :
Let The 18 man can build the remaining wall in d days
Time taken by 12 men to build a wall = 15 days
i.e 12 men in 15 days make 1 wall
Or, 12 men in 1 day make wall
∴, 12 men in 3 days make × 3 wall
i.e 12 men in 3 days make wall
Again
Contractor bring team of 18 men to complete the remaining work
Remaining work = 1 -
Or, Remaining work =
∴ Remaining work =
Now,
∵ = constant
So, =
Or, 4 × 12 × 3 = 18 × d
∴, d =
i.e d = 8 days
So, The time taken by 18 men to build the remaining wall = d = 8 days
Hence, The time taken by 18 men to build the remaining wall is 8 days . Answer
Similar questions
Political Science,
5 months ago
Hindi,
5 months ago
Sociology,
10 months ago
Chemistry,
10 months ago
Math,
1 year ago