12 men can complete 1/3 of work in 8 days.then how many days 16 men can do that work

Answers

Answered by santy2
0

12 men complete 1/3 of the work in 8 days.

How many days do they take to complete the entire work:

1/3 = 8 days

1 =?

We use 1 to represent the entire work since fractions when added gives a whole number.

1 × 3/1 × 8 = 24 days

12 men take 24 days to complete the work

16 men will take how long:

12 : 24

16 :?

12/16 × 24

12/16 × 24 = 18 days