12 men can complete a piece of work in 18 days. All of them started the work together and after 6 days 4 more laborers joined the work. In how many days will the remaining work be completed?
Answers
Answered by
1
Answer:
12 men can do a work in = 18 days
they worked for 6 days
the total amount of work = no. of people x no of days
total work = 18 x 12
total work = 216
so in 18 days the amount of work done will be = 216
so in 6 days the amount of work done will be = 72
remaining work = 216 - 72 = 144
so after 6 days no of people = 16
let the no. of days they worked for = x
ATQ,
144 = 16* x
x = 9
so the no. of days = 9
Answered by
0
Answer:
the no of day is 9
Step-by-step explanation:
work done by the formula
144-16*=9
ans=9