Math, asked by karthikkottu302, 10 months ago

12 men can complete a work in 10 days and 15 women can complete a work in 12 days. in how much time 8 men and 12 women can complete the same work

Answers

Answered by LitChori01
9

Answer:

Step-by-step explanation:

Men :-

If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.

12/8 × 10

= 15 days

It will take 8 men 15 days to complete this work.

Women:-

If there are more women so it will take less number of days but if there are less women it will take more days to complete the work.

15/12 × 12

= 15 days

It will take 15 days for 12 women to complete the work.

Answered by Anonymous
2

Men :-

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10= 15 days

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10= 15 daysIt will take 8 men 15 days to complete this work.

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10= 15 daysIt will take 8 men 15 days to complete this work.Women:-

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10= 15 daysIt will take 8 men 15 days to complete this work.Women:-If there are more women so it will take less number of days but if there are less women it will take more days to complete the work.

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10= 15 daysIt will take 8 men 15 days to complete this work.Women:-If there are more women so it will take less number of days but if there are less women it will take more days to complete the work.15/12 × 12

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10= 15 daysIt will take 8 men 15 days to complete this work.Women:-If there are more women so it will take less number of days but if there are less women it will take more days to complete the work.15/12 × 12= 15 days

Men :-If there are more men so it will take less number of days but if there are less men it will take more days to complete the work.12/8 × 10= 15 daysIt will take 8 men 15 days to complete this work.Women:-If there are more women so it will take less number of days but if there are less women it will take more days to complete the work.15/12 × 12= 15 daysIt will take 15 days for 12 women to complete the work.

Similar questions