' 12 men Can Complete a work in 8 days. 16 men can Complete the work in 12 days 8 Men and 8 women started worked for 6 days. How many more men are to be added Complete the remaining work in 1 day
Answers
Answered by
0
Answer:
mark me brainlist
Step-by-step explanation:
To complete the work =8 x12= 96 man-hours are required.
To complete the same work= 16 x 12= 192 woman- hours are required.
So 1 man- hour= 192/96= 2- woman -hours.( Or)
1 woman -hour= 1/2 man-hours
8 men+ 8 women= (8 +8/2)= 12 man - hours.
If they work 6-days the amount of work done= 12 x 6= 72 man - hours.
The remaining work consists of =(96–72)= 24
If 24- man-hours work is to be finished in 1- day then 24 men will be required.
Already 8 men + 8 women are working which is equivalent to 12- men.
So more men required = (24–12)= 12
Answered by
0
Answer:
fff
Step-by-step explanation:
Similar questions