Math, asked by vermadashrath9331, 1 year ago

12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work?

Answers

Answered by rishabh8728
2

-12 men can do 12 unit of work

-therefore in 90 days = 90 × 12

= 1080 unit

-therefore in 30 days = 30 × 12

= 360 unit

-remaining work = 1080 - 360

= 720 unit

-amount of work = 18 unit per day

done by 18 work

days remaining = 720/18

= 40

therefore 40 days it will take to complete the remaining work