12 men can complete one third of the work in 8 days. In how many days can 16 men complete the work?

Answers

Answered by januja74
2
12×8=16×x
X=12×8/16
X=6
answer= 6 days

redum: in book answer is showing 18? ...is 18 is wrong?
januja74: i think mine is correct
redum: thnkz...
januja74: welcome
januja74: anyway u report my answer so that you be clear.
redum: K...
redum: actually m very poor in maths...
januja74: ok