12 men can complete work in 18 days. 6 days after they started working, 4 men joined them. how many days will all of them take to finish the remaining work?

Answers

Answered by saziyakhan
1

Answer:

If 12 men can complete work in 18 day it means the job requires the input of 12*18=216 man days in six days the work completed means 12*6=72 man days of work