12 men can do a work piece of work in 15 days how many men are required to complete the work in 10 days
Answers
Answered by
2
Answer:
Its your answer.
May it help you. Mark brainliest.
Attachments:
Answered by
0
Answer:
8 men
Step-by-step explanation:
Men(x) Days (y)
12 15
? 10
Indirect proportion
x1 = y1
x2 y2
=> 12 = 15 => x2 = 15
x2 10 12 10
x2 => 12 x 15 = 8 men
10