12 men can finish a piece of work in 8 days. how many days will it take 6 men to do the same working at the same time?
Answers
Answered by
0
Answer:
10 days
plz follow me bro
you are so smart if you give me brainliest and follow me
Answered by
0
Answer: 16
Step-by-step explanation:(12×8)/6
96/6
16