12 men can hole a field in 10 days . how many long will 15 mn take
Answers
Answered by
0
Answer:
6
Step-by-step explanation:
12×10 = 15 ×x
12×10/15=x
4×2 =
6
so 6 days are needed for 15 men
Answered by
1
Answer:
As given in the question that 12 men can hoe a field in 10 days.
we have to find how long will 15 men take.
Now,
1 man can hoe a field = 10 x 12
= 120 days
15 men can hoe a field = 120/15
= 8 days
Therefore, 15 men can hoe a field in 8 days.
Please mark me the brainliest and Rate me and give me thanks.